Utah wind farms
Utah has 9 wind projects with 208 turbines and 391 MW of capacity, ranking #29 among US states and territories for installed wind. The largest is Milford Phase I in Beaver County at 204 MW.
- Wind projects
- 9
- Turbines
- 208
- Capacity
- 391 MW
- National rank
- #29
Map of Utah wind projects
Top counties for wind
Counties with existing wind farms already have the roads, permits and grid connections that developers look for.
| County | Capacity | Turbines |
|---|---|---|
| Beaver County | 204 MW | 97 |
| Millard County | 102 MW | 68 |
| San Juan County | 62 MW | 27 |
| Utah County | 20 MW | 14 |
| Tooele County | 3 MW | 2 |
Thinking about a wind lease in Utah?
The most recent project in the database, Latigo, came online in 2016. If a developer has approached you, compare their offer against what you can learn about your own wind and the projects around you.
Rules on setbacks, decommissioning and how turbines are taxed differ between states and counties. Ask an independent Utah attorney who has reviewed wind agreements, and check with your county about local wind ordinances.
All Utah wind projects
| Project | County | Capacity | Turbines | Hub height | Online |
|---|---|---|---|---|---|
| Milford Phase I | Beaver County | 204 MW | 97 | 80 m | 2009 |
| Milford Phase II | Millard County | 102 MW | 68 | 80 m | 2011 |
| Latigo | San Juan County | 62 MW | 27 | 80 m | 2016 |
| Spanish Fork | Utah County | 19 MW | 9 | 79 m | 2008 |
| Tooele Army Depot II | Tooele County | 2 MW | 1 | 80 m | 2016 |
| Shakopee Mdewakanton Sioux | Tooele County | 2 MW | 1 | 80 m | 2009 |
| Camp Williams | Utah County | 1 MW | 2 | 40 m | 2000–2005 |
| Unnamed project | Utah County | – | 2 | – | – |
| Unnamed project | Utah County | – | 1 | – | 2015 |
Source: U.S. Wind Turbine Database from the U.S. Geological Survey, Lawrence Berkeley National Laboratory and the American Clean Power Association, retrieved 2026-11-19. Includes land-based and offshore turbines that are built or under construction. Projects built in phases are combined; dots show the average location of each project's turbines.